New Kitchen Addition
Here are weekly photos of the new kitchen addition to the west end of the existing kitchen.
October 2nd photos. Digging out and forming up the walls
Here are weekly photos of the new kitchen addition to the west end of the existing kitchen.
October 2nd photos. Digging out and forming up the walls
Week ending of October 9th, 2011
Week of October 16th:
These photos are from work done on
Monday, October 17th.
When I took these pictures (Tuesday, Oct. 18th) I saw trusses next to the building. I am hoping by Sunday that they will be up, but have a big doubt that they will. The weather may not be on our side this week. It is looking good and taking good shape!!
Below pictures are the
Week ending October 23
Below are Pictures for Week ending October 30th
Brick will start being laid in about two weeks. (Week starting November 7) Work done by members of Zion-Lippe Congregation. Needing helpers for Hod Carrying/making Mud. Contact Tim Hoenert or Jack Kleiman for details.
For the week ending November 6th, there has not been much change in apperance for the Kitchen. There will be a start in brick laying this week, weather permiting. Please pray that the rain 'go around' us and let the men work steadily!!
Week ending November 13th.
Way to go Brick Layers, almost done an it looks great!!! Most of the doors and all windows are in. Time to get it closed up and work indoors soon.
Way to go Brick Layers, almost done an it looks great!!! Most of the doors and all windows are in. Time to get it closed up and work indoors soon.
The week ending November 19th
Not much to see, except the brick is all finished.
Wonder if the whole project will be finished in the year 2011?
Not much to see, except the brick is all finished.
Wonder if the whole project will be finished in the year 2011?
Week ending November 26th to Present
Not much to see, but did take a few pictures of the project.
Waiting on a good picture of the doors to be put in!!
Not much to see, but did take a few pictures of the project.
Waiting on a good picture of the doors to be put in!!
Week ending December 16th
I did hear that drywall and the front doors are in the works of being installed very soon. We will see what the Holiday's are in store for us!!
Merry Christmas to you all!!
I did hear that drywall and the front doors are in the works of being installed very soon. We will see what the Holiday's are in store for us!!
Merry Christmas to you all!!
Week ending January 8th
Painting and Range Hood
The painting is finished and the range hood is in. The door way from old kitchen to new kitchen has been widend. The pass thru is open but has cardboard to keep it closed for now. Wood is being stained, for I guess the stairs.